TTAB Cancellations 92061741
USPTO Cancellations proceeding 92061741, filed 2015-06-29. Status: Terminated.
Proceeding Facts
| Proceeding Number | 92061741 |
|---|---|
| Type | Cancellations |
| Status | Terminated |
| Filing Date | 2015-06-29 |
| Last Activity | 2016-04-06 |
| Days Active | 3975 |
Parties
- Plum Creek Development Partners, Ltd. dba Plum Creek — Defendant
- Plum Creek Timber Company, Inc. — Plaintiff
Plaintiff Marks
- PLUM CREEK — Plum Creek Timber Company, Inc.
- PLUM CREEK — Plum Creek Timber Company, Inc.
Defendant Marks
- PLUM CREEK — Plum Creek Development Partners, Ltd. dba Plum Creek
Recent Documents
- 2016-04-06: TERMINATED — Status
- 2016-04-06: BD DECISION: DISMISSED W/O PREJ — Decisions
- 2016-04-01: W/DRAW OF PET FOR CANCELLATION — Miscellaneous
- 2016-03-31: RESPONSE DUE 30 DAYS (DUE DATE) — Scheduling
- 2016-03-23: W/DRAW OF PET FOR CANCELLATION — Miscellaneous
- 2016-01-14: SUSPENDED — Status
- 2016-01-14: P MOT TO SUSP W/ CONSENT PEND SETTL NEGOTIATIONS — Motions
- 2016-01-12: TRIAL DATES REMAIN AS SET — Scheduling
- 2015-12-16: D MOT TO SUSP W/ CONSENT PEND SETTL NEGOTIATIONS — Motions
- 2015-10-02: SUSPENDED — Status
- 2015-09-21: ANSWER — Pleadings
- 2015-08-14: D MOT TO SUSP W/ CONSENT PEND SETTL NEGOTIATIONS — Motions
- 2015-08-13: P MOT TO AMEND PLEADING/AMENDED PLEADING — Motions
- 2015-08-10: ANSWER — Pleadings
- 2015-07-28: D UNDELIVERABLE MAIL — Correspondence
- 2015-06-30: PENDING, INSTITUTED — Status
- 2015-06-30: NOTICE AND TRIAL DATES SENT; ANSWER DUE: — Scheduling
- 2015-06-29: FILED AND FEE — Fees